News 27th April

Pennywell Road, Bristol:

Solid Timber Frame has been completed. Sustainable Homes Code Level 4 and completion on program are both on target for successful delivery.

Wade Street, Bristol:

Works completed up to slab level. Timber Frame is due to be delivered w/c 27th April 2009.

Organic Power Projects:

Commercialisation Process Continues.

Barrow Hospital Redevelopment:

Commercial support to Planning Stages of 300 acre site continues.

Bottelinos Portishead Development -:

Plans to commence construction of superstructure in August 2009 underway.